Seven California Community Power Members Contract for 69 Megawatts of Long Duration Energy Storage

Seven California Community Power Members Contract for 69 Megawatts of Long Duration Energy Storage

Project marks first major procurement milestone for CCA Joint Powers Agency

 

Monterey, Calif. – At the January 19 California Community Power (CC Power) board meeting, members of the Joint Powers Agency voted to enter into an energy storage service agreement with REV Renewables for 69 megawatts (MW)/552 megawatt hours (MWh) of long-duration energy storage. The REV Renewables Tumbleweed project will be a CAISO grid-connected, lithium-ion battery storage resource located near Rosamond, in Kern County, California, with an expected online date of 2026.

 

“Long-duration energy storage is a vital resource, needed to amplify the value of renewable power, and accelerate California’s shift to a clean, reliable and affordable grid,” said Girish Balachandran, California Community Power Board Chair and Silicon Valley Clean Energy CEO. “This first project is an exciting milestone that shows how CCAs work together to advance our shared goals in the transition to a carbon-free grid.

 

The California Public Utilities Commission Mid-Term Reliability Procurement order (Decision 21-06-035) requires all CPUC-jurisdictional load serving entities, including CC Power Members, to procure from energy storage facilities capable of discharging for a minimum of 8 hours. This project satisfies approximately 55% of the long-duration storage compliance requirements of the participating members.

 

This joint procurement effort for long-duration energy storage began before the CPUC issued the new procurement order when a subset of the CC Power members issued a Request for Offers (RFO) in Oct. 2020 seeking to procure cost effective and viable long-duration storage resources.

 

Participating CCAs

Participating CCA Members

Participation in the RFO and resulting projects is voluntary for each CC Power member. The participating agencies for this project are CleanPowerSF, Peninsula Clean Energy, Redwood Coast Energy Authority, San Jose Clean Energy, Silicon Valley Clean Energy, Sonoma Clean Power Authority and Valley Clean Energy. Participating members will follow their own review and approval processes with their local, elected boards.

 

The Tumbleweed project adheres to the long-duration storage enhanced conditions adopted by the CC Power Board for this procurement effort. It will be constructed under a Project Labor Agreement, assuring prevailing wages and use of apprenticeship programs and is expected to create dozens of new jobs.

 

The ongoing RFO process, as well as member participation have been discussed during noticed, public meetings of the CC Power board. Additional projects identified during the competitive solicitation process will be discussed at upcoming meetings. Meeting information is available at cacommunitypower.org/meetings.

 

###

 

About California Community Power

California Community Power is a Joint Powers Agency comprised of ten California Community Choice Aggregators (CCAs). The agency allows its member CCAs to combine their buying power to procure new, cost-effective clean energy and reliability resources to continue advancing local and state climate goals. California Community Power members represent over 3 million customers across more than 145 municipalities spanning from Humboldt County to Santa Barbara County. Learn more at cacommunitypower.org.

 

Media Contact

Pamela Leonard
Communications Manager
Silicon Valley Clean Energy
pamela.leonard@svcleanenergy.org
O: 408-721-5301 x1004

Related posts

California Community Power Members Approve Second Lithium-Ion Long-Duration Energy Storage Contract

Six CCAs sign on to new California lithium-ion storage project Monterey, Calif. – At a special meeting of the California Community Power (CC Power) board on February 25, members of the Joint Powers Agency voted to enter into a contract for the 50-megawatt (MW)/400-megawatt hour (MWh) Goal Line long-duration energy storage project. The lithium-ion

Read More

California Community Power Releases Request for Offers Seeking 200 MW of Firm Clean Resources

Proposals due December 2021 Monterey, Calif. – California Community Power (CC Power) has issued a Request for Offers (RFO) for up to 200 megawatts (MW) of Firm Clean Resources through one or more projects, with deliveries beginning no later than June 1, 2026. Firm Clean Resources produce renewable energy on demand and include geothermal

Read More